POSCO MEXICO POWER GENERATION PLANT

InTime Control S.A. de C.V. participated in this project as an electric sub-contractor. The plant has 3 power generators with 3MW capacity.

The project was started on Jan 18, 2010 and finished on Jun 30, 2010.

The major activities of electrical work are:

Electrical & instrument works for power generation plant.

  1. Installation of electrical equipments

  2. Installation of cable route

  3. Cabling and termination

  4. Electrical tie-in to the main incoming bus

  • Commissioning

  • Installation of instrument and commissioning